Howdy all,I had the footings poured last summer for my 12 x 24 shop addition and then poured the floor before winter set in. Last winter, due to the floor heaving, the inside of the footers were chipped off to about the center of the 10" wide footers and also the outside edge where the sidewalk contacts the footer. The 24' footer between the floor and sidewalk now resembles an inverted "V". I need too fill in and repair the 1/2" to 2" deep sections so I have a level, flat base for my walls to seal against. I have the usual blue footer foam rolls, but the walls will only contact about 2" of the concrete footer in many places. Whats a good way to build up the footer? What is the best material (concrete, portland cement, etc.) to use? Just trowel something in and hope it finds its own level? I can't dig up the ground and put in new forms for the obvious reasons. Thanks for all the help, ALL opinions greatly appreciated! Scott
|