Sort of lucked out early as I sold alot of the rack. Now I have to stack in earnest. Hay stacking a one man job? The way things are these days finding some help to get the hay in the barn is a job all its self. I have found a few kids that are interested in making a few extra dollars, That is until you need them then they are busy. Pretty much it has been just me.One benefit I do have is I can park my 4 racks under cover until I have time to unload. If I could not do this I don't think I could do hay. One of my biggest problems has been spoilage of the bottom row of bales in the stack. lost about 250 bales, at $3 a bale that's a pretty big loss. Plus I have prepay customers that I store their hay until needed. This is a problem if you don't have replacement bales. I have tried a layer of hay under the bottom and got mold I have tried a layer of hay and a pallet and still got mold. This year I am trying some thing new. 
 I start by building my stack as high as I can comfortably from the ground. 5 high for me. Then I set up my elevator. I did not have this last year. I used a step design for my stack, whew that was a whole lot of work. Normally I would set this up on a rack and off load right from the rack. I didn't have help today so I unloaded onto the ground then placed on the elevator. Could get about 15 or 20 bales up then I would stack them. Repeat as needed.

IMG SRC="http://ns2.genesis-technology.com/~kvp/images/8-18-05/Stacking2.jpg"> I have a few racks to get done so I better get at it.
|